Home / Planning Guides / Deadline calculator
Tool

Planning Deadline Calculator

The key statutory deadlines on a planning file, from a planning reference or the dates on the file.

Information, not advice. A late appeal or submission is invalid. Check any date against the decision notice, the planning authority or An Coimisiún Pleanála, and lodge early. Much of the law described here is new and has not yet been tested in the courts or by An Coimisiún Pleanála, and it could be affected by challenge, amendment or further regulation. This page gives our reading of it. For a definitive answer on a particular property or application, engage with the relevant planning authority.
The reference on the site notice or the council's planning portal. Applications from 2013 onward, all 31 planning authorities.

How the Dates Are Counted

  • The first day counts. A period "beginning on" the day of receipt or decision includes that day.
  • Christmas is left out. 24 December to 1 January is not counted (s.251 of the 2000 Act; s.402(1) of the 2024 Act). Judicial review is shown without this.
  • Closed days. A last day on a weekend or public holiday moves to the next working day, except a submission to the council under the 2000 Act, which has no such rule.
  • Where the wording allows two readings, the earlier date is shown.

What It Does Not Cover

Further information, significant further information, strategic infrastructure, large-scale residential development, and applications with an EIAR or NIS all change the periods. Recent decisions may not yet be on the register; enter the dates by hand. See appealing a decision and making a submission.

Sources: Planning and Development Act 2000, ss.34(8), 37(1) and (6), 50(6), 50AA, 130(3), 141 and 251, and article 29 of the Planning and Development Regulations 2001; Planning and Development Act 2024, ss.97, 101(11), 102, 281, 360, 365 and 402, Law Reform Commission revised texts; draft Planning and Development (Control of Development (Planning Authorities)) Regulations 2026, reg. 17. Register data: National Planning Application Database (data.gov.ie, CC BY 4.0). The Commission's own appeal calendar gives the appeal date only.

The Periods the Calculator Uses

The 2000 Act applies to applications lodged before Part 4 of the 2024 Act commences; the 2024 Act to those lodged on or after.

Deadline2000 Act2024 Act
Submission to the council5 weeks beginning on the date of receipt, with the €20 fee. Article 29, 2001 Regulations.5 weeks beginning on the date of receipt, on Form No. 5 with the Form No. 6 declaration. Draft reg. 17(1) under s.97(1), not yet made.
Decision due (no further information)8 weeks beginning on the date of receipt. s.34(8)(a).8 weeks from the date of the application, where no AA or EIA is needed. s.101(11)(a)(i).
Appeal to An Coimisiún Pleanála4 weeks beginning on the day of the decision. s.37(1)(d). Open to the applicant and anyone who made a submission.Within 4 weeks of the decision, decision day counted. s.360(1)(b). A third party appeal needs the s.588 declaration.
Adjoining landowner: leave to appealWithin the same 4 weeks, against a grant only. If leave is granted, the appeal follows within 2 weeks. s.37(6).No equivalent.
Observation or submission on the appeal4 weeks beginning on the day the Commission received the appeal (the last one, if more than one). s.130(3)(c).Within 5 weeks of the last day for appealing. s.365(2)(b)(i).
Judicial review of the council's decision8 weeks beginning on the date of the decision, for applications made on or after 12 August 2026. s.281 of the 2024 Act, applied by s.50AA of the 2000 Act.
8 weeks beginning on the date of the decision, with a leave stage. s.50(6) of the 2000 Act, for applications made before 12 August 2026.
8 weeks beginning on the date of the decision. s.281.

A Public Information Service

These guides and tools are published as a public service and are kept to the primary legislation. They are not a free advice line, and individual queries are not answered by email or phone. For a general question about a particular property, the planning authority's planning department and Citizens Information are the starting points, and a declaration under section 5 is the formal answer. Where a matter needs professional work, the practice takes instructions on a fee basis: from developers, landowners, investors and public bodies, and from private clients, for example on retention or regularisation of unauthorised development or a change of use, and occasionally a one-off house, subject to capacity.