The key statutory deadlines on a planning file, from a planning reference or the dates on the file.
Further information, significant further information, strategic infrastructure, large-scale residential development, and applications with an EIAR or NIS all change the periods. Recent decisions may not yet be on the register; enter the dates by hand. See appealing a decision and making a submission.
The 2000 Act applies to applications lodged before Part 4 of the 2024 Act commences; the 2024 Act to those lodged on or after.
| Deadline | 2000 Act | 2024 Act |
|---|---|---|
| Submission to the council | 5 weeks beginning on the date of receipt, with the €20 fee. Article 29, 2001 Regulations. | 5 weeks beginning on the date of receipt, on Form No. 5 with the Form No. 6 declaration. Draft reg. 17(1) under s.97(1), not yet made. |
| Decision due (no further information) | 8 weeks beginning on the date of receipt. s.34(8)(a). | 8 weeks from the date of the application, where no AA or EIA is needed. s.101(11)(a)(i). |
| Appeal to An Coimisiún Pleanála | 4 weeks beginning on the day of the decision. s.37(1)(d). Open to the applicant and anyone who made a submission. | Within 4 weeks of the decision, decision day counted. s.360(1)(b). A third party appeal needs the s.588 declaration. |
| Adjoining landowner: leave to appeal | Within the same 4 weeks, against a grant only. If leave is granted, the appeal follows within 2 weeks. s.37(6). | No equivalent. |
| Observation or submission on the appeal | 4 weeks beginning on the day the Commission received the appeal (the last one, if more than one). s.130(3)(c). | Within 5 weeks of the last day for appealing. s.365(2)(b)(i). |
| Judicial review of the council's decision | 8 weeks beginning on the date of the decision, for applications made on or after 12 August 2026. s.281 of the 2024 Act, applied by s.50AA of the 2000 Act. 8 weeks beginning on the date of the decision, with a leave stage. s.50(6) of the 2000 Act, for applications made before 12 August 2026. | 8 weeks beginning on the date of the decision. s.281. |
These guides and tools are published as a public service and are kept to the primary legislation. They are not a free advice line, and individual queries are not answered by email or phone. For a general question about a particular property, the planning authority's planning department and Citizens Information are the starting points, and a declaration under section 5 is the formal answer. Where a matter needs professional work, the practice takes instructions on a fee basis: from developers, landowners, investors and public bodies, and from private clients, for example on retention or regularisation of unauthorised development or a change of use, and occasionally a one-off house, subject to capacity.